Central Puerto S.A. Mendoza Site

Our plant has an installed capacity of 509 MW and 10 units:

  • A Combined Cycle (CC) that is composed of a Siemens gas turbine and a Skoda steam turbine, totaling 306 MW.
  • An Alstom cogeneration unit and two Mecánica de la Peña Heat Recovery Steam Generators (‘HRSG’) with additional burners and a capacity of 46 MW and 150 tn/h of steam.
  • An ABB Combined Cycle (CC) of 36 MW.
  • Two Marelli steam turbines [“TV”, for its Spanish acronym] of 60 MW each.
  • A mini hydraulic power station with turbine and Ossberger generator of 1 MW.

We also have a Siemens cogeneration unit of 93 MW and 125 tn/h of steam production capacity currently under construction. Commercial operation date: November 2019 (expected).

Plant Surface: 50 ha